Utrecht Availability
Installation Data:
Installation data Eneco Warmteproductie Utrecht :
LW06 :  capacity 247 MW.  Gas fired CHP.  Location : Atoomweg 7-9 Utrecht Netherlands.   Connection with Tennet at 150kV station Lage Weide.
MK12 :  capacity 224 MW.  Gasfired CHP.  Location : Merwedekanaal 181 Utrecht Netherlands. Connection with Tennet at 150kV station Lage Weide. 
Publication Date Time
Asset
Start Date Time
End Date Time
Available Capacity
TypeReason
01-11-2019 11:58:34
LW06
01-09-2020 00:00:00
11-09-2020 23:59:30
0.00 MW
Planned
A- inspection
01-11-2019 11:55:38
MK12
01-10-2020 00:00:00
20-11-2020 00:00:00
0.00 MW
Planned
C inspection
25-09-2019 14:12:00
MK12
26-09-2019 08:00:00
27-09-2019 15:00:00
0.00 MW
Planned
Replacement kWh-measurement equipment
27-08-2019 12:40:37
MK12
27-08-2019 12:40:43
30-08-2019 18:00:00
0.00 MW
Planned
maintenance
27-08-2019 12:29:50
LW06
27-08-2019 12:30:01
29-08-2019 18:00:00
0.00 MW
Planned
maintenance
24-07-2019 18:38:21
MK12
24-07-2019 18:00:00
24-07-2019 21:00:00
0.00 MW
Unplanned
GT trip during start up 
24-07-2019 16:13:04
MK12
31-07-2019 21:00:00
01-08-2019 21:00:00
0.00 MW
Planned
Repairs oil lekkeage Trafo 6KV
24-07-2019 15:08:21
MK12
24-07-2019 15:08:00
24-07-2019 18:00:00
0.00 MW
Unplanned
Flame detection GT
16-07-2019 10:17:00
MK12
15-07-2019 12:00:00
31-07-2019 12:00:00
155.00 MW
Unplanned
Failure 1 cooling water pump
10-07-2019 15:01:31
MK12
12-07-2019 12:00:00
31-07-2019 12:00:00
150.00 MW
Unplanned
failure 1 cooling water pump
03-07-2019 22:07:49
MK12
03-07-2019 22:07:53
11-07-2019 00:00:00
0.00 MW
Unplanned
Trouble with cooling condensor pump
25-06-2019 16:13:33
MK12
26-08-2019 00:00:00
06-09-2019 23:59:00
0.00 MW
Planned
STEDIN maintenance Trafo ULW150
27-05-2019 17:50:02
MK12
27-05-2019 17:00:00
28-05-2019 14:30:00
0.00 MW
Unplanned
Problems with GT gas valve
24-05-2019 09:34:15
MK12
24-05-2019 09:34:23
27-05-2019 13:00:00
0.00 MW
Unplanned
Boiler leakage
01-05-2019 14:53:48
MK12
01-05-2019 14:53:50
24-05-2019 08:00:00
0.00 MW
Planned
Overhaul
01-05-2019 14:46:10
LW06
01-05-2019 13:01:14
01-05-2019 15:30:39
0.00 MW
Planned
SSI
01-05-2019 10:54:46
LW06
01-05-2019 12:00:00
01-05-2019 13:00:00
0.00 MW
Planned
rensec delayed
30-04-2019 19:59:16
LW06
30-04-2019 19:59:25
01-05-2019 12:00:00
0.00 MW
Planned
RENSEC testing synchronising for black start unit
30-04-2019 17:54:23
LW06
30-04-2019 17:56:24
30-04-2019 20:00:00
0.00 MW
Planned
RENSEC testing synchronising for black start unit
30-04-2019 14:02:31
LW06
30-04-2019 14:02:37
30-04-2019 18:00:00
0.00 MW
Planned
RENSEC testing synchronising for black start unit
26-03-2019 12:39:25
MK12
27-03-2019 08:00:00
27-03-2019 10:00:00
0.00 MW
Planned
Due to test program brown start
25-03-2019 19:53:24
MK12
26-03-2019 05:30:00
26-03-2019 13:00:00
0.00 MW
Planned
Because off problem with GT6 excitation problem!
25-03-2019 13:08:24
MK12
25-03-2019 12:00:00
26-03-2019 05:30:00
120.00 MW
Unplanned
Power restricted to 120 MWe due to GT exitation problem
24-03-2019 22:06:04
MK12
24-03-2019 21:00:24
25-03-2019 12:00:00
120.00 MW
Unplanned
power restricted to 120 MWe due to GT exitation problem
22-03-2019 10:23:24
MK12
01-05-2019 00:00:00
24-05-2019 18:00:00
0.00 MW
Planned
planned outage for maintenance
15-03-2019 14:40:26
MK12
15-03-2019 08:00:00
15-03-2019 16:00:00
0.00 MW
Unplanned
Work completed earlier than planned
14-03-2019 16:49:57
MK12
14-03-2019 16:00:00
15-03-2019 08:00:00
0.00 MW
Planned
GT rotor got stuck
14-03-2019 09:00:15
MK12
14-03-2019 08:00:21
14-03-2019 16:00:25
0.00 MW
Unplanned
rotor GT got stuck
13-03-2019 17:00:35
MK12
13-03-2019 16:00:00
14-03-2019 08:00:00
0.00 MW
Unplanned
rotor GT got stuck
01-03-2019 11:43:48
LW06
08-03-2019 15:00:00
12-03-2019 15:00:00
0.00 MW
Planned
repair High pressure boiler


26-02-2019 18:31:53
MK12
26-02-2019 17:30:00
26-02-2019 22:00:00
0.00 MW
Unplanned
Low SF6 pressure of 150kV switch
23-01-2019 20:26:48
LW06
23-01-2019 22:00:00
23-01-2019 23:59:59
0.00 MW
Planned
Change out electronica For two hours
13-01-2019 22:06:10
LW06
13-01-2019 21:06:16
13-01-2019 21:06:19
0.00 MW
Unplanned
Luvo repaired ready to start LW#06
12-01-2019 19:03:32
LW06
12-01-2019 18:05:26
14-01-2019 00:00:00
0.00 MW
Planned
Extended planned outage for repair LUVO.  
11-01-2019 10:50:19
LW06
11-01-2019 23:00:00
12-01-2019 23:59:00
0.00 MW
Planned
Planned outage for repair LUVO
31-12-2018 16:49:39
MK12
31-12-2018 15:49:49
03-01-2019 14:00:00
0.00 MW
Unplanned
Malfunction gasvalve GT ( turbine temp. regulator )
20-12-2018 13:26:25
MK12
20-12-2018 12:26:31
20-12-2018 18:00:00
0.00 MW
Planned
Trip due to gas controlvalve problems
20-12-2018 11:38:10
MK12
20-12-2018 10:38:43
20-12-2018 13:00:00
0.00 MW
Unplanned
Trip due to gas controlvalve problems
18-12-2018 23:16:46
MK12
18-12-2018 22:00:00
20-12-2018 11:00:00
0.00 MW
Unplanned
Trip due to gas controlvalve problems
17-12-2018 15:03:24
MK12
17-12-2018 14:00:00
18-12-2018 22:00:00
170.00 MW
Unplanned
Power reduction due to gas controlvalve problems.
16-12-2018 18:27:24
MK12
16-12-2018 17:30:27
17-12-2018 14:00:00
185.00 MW
Unplanned
Gascontrol valve malfunction due to air in hydraulic system
15-12-2018 04:48:57
MK12
14-12-2018 23:00:00
16-12-2018 17:30:00
0.00 MW
Planned
Change of lubrication oil Gasturbine GT06
14-12-2018 21:22:38
MK12
14-12-2018 22:00:41
14-12-2018 23:00:00
0.00 MW
Unplanned
trip during start up
14-12-2018 18:41:53
MK12
14-12-2018 16:00:56
14-12-2018 22:00:30
0.00 MW
Unplanned
trip during start up
04-12-2018 11:00:46
MK12
07-12-2018 23:00:00
14-12-2018 16:00:00
0.00 MW
Planned
Outage  for planned change of lubrication oil GT06
10-11-2018 01:12:18
LW06
10-11-2018 01:00:00
10-11-2018 18:00:00
0.00 MW
Planned
Planned outage
06-11-2018 21:58:33
MK12
06-11-2018 20:58:53
07-11-2018 01:50:00
0.00 MW
Unplanned
Trip due differentz MAX1 VIGV's.
02-11-2018 09:05:04
MK12
02-11-2018 10:00:00
02-11-2018 15:00:00
0.00 MW
Unplanned
Malfunction gas control valve
02-11-2018 09:02:43
MK12
02-11-2018 08:00:00
02-11-2018 10:00:00
109.00 MW
Unplanned
Unit will not follow setpoint
01-11-2018 12:00:31
LW06
01-04-2019 00:00:00
30-04-2019 07:00:00
0.00 MW
Planned
Due to Tennet revision 150kV station Lage Weide ( Rensec ).
1 to 50 of 57 records
previous12next
Disclaimer: This information is given based on the best estimate of Eneco and has no pretense of being reliable or representative for any market developments. Any use of this information, as a whole or any part thereof, by any person or company without the EXPLICIT consent of Eneco is for that persons or companies own risk and responsibility. Eneco makes no representation or warranty of any kind concerning accuracy or other potential errors in the information. Eneco disclaims all warranties with regard to this information. In no event shall Eneco be liable for any specific, indirect or consequential damages whatsoever resulting from loss profits caused by, or in connection with, the use of this information.