Windpark Availability
Installation Data:
Windpark Luchterduinen: Capacity 129 MW. High Wind Stop setting 25 m/s.
Princes Amalia Windpark: Capacity 120 MW. High Wind Stop setting 25 m/s, Ambient Temperature Stop >31 °C.
For the High Wind Stop and Ambient Temperature Stop we wish to point out that these will be automatically triggered based on local measurements. As weather forecasts by definition have an uncertainty, the shut-down of (parts of) the windfarms will in most cases be abrupt. 
Publication Date Time
Asset
Start Date Time
End Date Time
Available Capacity
TypeReason
31-03-2020 19:23:56
Prinses Amalia Windpark
31-03-2020 17:00:58
31-03-2020 20:00:16
0.00 MW
Unplanned
30-03-2020 14:47:11
Prinses Amalia Windpark
31-03-2020 08:00:00
31-03-2020 17:00:00
0.00 MW
Planned
Maintenance
27-03-2020 10:24:19
Luchterduinen
21-04-2020 08:00:00
21-04-2020 16:00:00
0.00 MW
Planned
maintenance
27-03-2020 10:20:43
Luchterduinen
07-04-2020 08:00:00
07-04-2020 16:00:00
0.00 MW
Planned
maintenance
13-03-2020 13:39:40
Luchterduinen
16-03-2020 08:00:00
16-03-2020 12:00:00
0.00 MW
Planned
Maintenance 
16-02-2020 07:31:10
Luchterduinen
16-02-2020 07:31:13
16-02-2020 11:26:39
27.00 MW
Unplanned
high windspeed
15-02-2020 23:22:06
Prinses Amalia Windpark
15-02-2020 22:15:00
16-02-2020 00:01:00
16.00 MW
Unplanned
High Wind Speed
15-02-2020 22:16:17
Luchterduinen
15-02-2020 22:17:20
15-02-2020 00:00:00
0.00 MW
Unplanned
High windspeed
11-02-2020 04:59:09
Prinses Amalia Windpark
11-02-2020 04:59:15
11-02-2020 06:41:39
10.00 MW
Unplanned
High WindSpeed
10-02-2020 08:35:01
Luchterduinen
10-02-2020 08:35:20
10-02-2020 09:14:54
0.00 MW
Unplanned
High windspeeds
09-02-2020 10:08:01
Luchterduinen
09-02-2020 10:08:05
09-02-2020 21:36:56
0.00 MW
Unplanned
High Windspeed
09-02-2020 09:39:31
Prinses Amalia Windpark
09-02-2020 09:39:33
09-02-2020 22:05:27
0.00 MW
Unplanned
High Windspeed
11-11-2019 06:43:24
Luchterduinen
11-11-2019 07:00:27
11-11-2019 17:00:37
0.00 MW
Planned
Maintenance
04-11-2019 20:17:34
Luchterduinen
12-11-2019 17:00:00
14-11-2019 17:00:00
80.00 MW
Planned
maintenance.
04-11-2019 20:16:04
Luchterduinen
11-11-2019 17:00:00
12-11-2019 07:00:00
80.00 MW
Planned
maintenance
02-11-2019 19:33:19
Prinses Amalia Windpark
02-11-2019 19:33:27
02-11-2019 22:33:31
20.00 MW
Unplanned
High wind speed (>25 m/s)
30-10-2019 09:22:19
Luchterduinen
30-10-2019 08:30:00
30-10-2019 18:00:00
65.00 MW
Planned
maintenance
29-10-2019 17:50:14
Luchterduinen
31-10-2019 07:00:00
31-10-2019 18:00:00
0.00 MW
Planned
Scheduled maintenance
08-10-2019 08:00:42
Luchterduinen
29-10-2019 08:00:00
29-10-2019 17:50:00
0.00 MW
Planned
maintenance
01-10-2019 12:49:44
Prinses Amalia Windpark
17-10-2019 07:00:00
17-10-2019 15:30:00
0.00 MW
Planned
onderhoud
01-10-2019 12:48:11
Prinses Amalia Windpark
15-10-2019 07:00:00
15-10-2019 17:30:00
0.00 MW
Planned
onderhoud
01-10-2019 12:47:17
Prinses Amalia Windpark
14-10-2019 07:00:20
14-10-2019 17:30:35
0.00 MW
Planned
onderhoud
30-09-2019 12:10:24
Luchterduinen
07-10-2019 08:00:00
07-10-2019 17:00:00
0.00 MW
Planned
maintenance
23-09-2019 06:43:02
Luchterduinen
23-09-2019 08:00:05
23-09-2019 17:34:00
0.00 MW
Planned
Maintenance
10-08-2019 16:05:21
Luchterduinen
10-08-2019 16:10:19
10-08-2019 18:05:00
0.00 MW
Unplanned
high windspeed
10-08-2019 14:49:59
Prinses Amalia Windpark
10-08-2019 14:51:05
10-08-2019 17:50:00
0.00 MW
Unplanned
High windspeed
25-07-2019 14:56:23
Prinses Amalia Windpark
25-07-2019 14:00:00
26-07-2019 01:33:21
0.00 MW
Unplanned
All turbines stopped due Warm weather
05-06-2019 08:13:07
Luchterduinen
05-06-2019 08:13:10
05-06-2019 17:13:16
80.00 MW
Planned
Maintenance
07-05-2019 08:07:27
Prinses Amalia Windpark
07-05-2019 08:00:00
07-05-2019 17:37:00
0.00 MW
Planned
Maintenance HV and LV
10-04-2019 22:54:23
Luchterduinen
17-04-2019 08:00:00
17-04-2019 16:30:00
0.00 MW
Planned
Due to HV and LV maintenance full outage.
18-02-2019 12:58:27
Prinses Amalia Windpark
20-02-2019 08:00:00
20-02-2019 16:00:00
80.00 MW
Planned
High and low voltage maintenance
18-02-2019 12:56:45
Luchterduinen
19-02-2019 08:00:00
19-02-2019 09:00:00
0.00 MW
Planned
High and low voltage maintenance// maintenace cancelled. 
08-01-2019 10:29:44
Prinses Amalia Windpark
08-01-2019 06:29:57
08-01-2019 12:00:01
0.00 MW
Unplanned
windspeed above 25ms / chance on Storm disconect windturbines
07-08-2018 17:44:32
Prinses Amalia Windpark
07-08-2018 17:44:36
07-08-2018 21:31:58
0.00 MW
Unplanned
High ambient temprature. 31C + 
15-03-2018 14:46:04
Luchterduinen
15-03-2018 13:46:07
15-03-2018 16:17:00
0.00 MW
Unplanned
Trip Windfarm, cause unknown
18-01-2018 09:10:07
Prinses Amalia Windpark
18-01-2018 08:10:12
18-01-2018 12:54:41
0.00 MW
Unplanned
high windspeed
18-01-2018 07:52:32
Luchterduinen
18-01-2018 06:52:36
18-01-2018 12:54:34
0.00 MW
Unplanned
high wind speed
03-01-2018 10:36:54
Luchterduinen
03-01-2018 09:37:00
03-01-2018 14:23:42
0.00 MW
Unplanned
high wind speed
03-01-2018 10:36:28
Prinses Amalia Windpark
03-01-2018 09:36:33
03-01-2018 14:24:03
0.00 MW
Unplanned
high wind speed
05-10-2017 09:24:27
Prinses Amalia Windpark
05-10-2017 09:24:40
05-10-2017 12:00:00
0.00 MW
Unplanned
High Wind Speed
End time estimated 2019-02-12
18-09-2017 12:49:45
Luchterduinen
18-09-2017 08:00:00
18-09-2017 17:00:12
0.00 MW
Planned
HV works
13-09-2017 06:59:02
Prinses Amalia Windpark
13-09-2017 06:59:08
13-09-2017 13:17:00
0.00 MW
Unplanned
High wind speed (>25 m/s)
13-09-2017 06:42:04
Luchterduinen
13-09-2017 06:42:10
13-09-2017 13:16:51
0.00 MW
Unplanned
High wind speed (>25 m/s).
19-06-2017 08:55:00
Prinses Amalia Windpark
19-06-2017 09:00:36
19-06-2017 18:00:00
0.00 MW
Planned
HV Maintenance
23-02-2017 22:50:26
Prinses Amalia Windpark
23-02-2017 21:50:30
23-02-2017 23:10:40
0.00 MW
Unplanned
Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
23-02-2017 22:48:09
Luchterduinen
23-02-2017 21:49:41
23-02-2017 23:10:31
0.00 MW
Unplanned
Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
23-02-2017 21:15:59
Prinses Amalia Windpark
23-02-2017 20:16:04
23-02-2017 20:54:40
0.00 MW
Unplanned
Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
23-02-2017 13:38:00
Luchterduinen
23-02-2017 12:38:03
23-02-2017 21:28:20
0.00 MW
Unplanned
Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
23-02-2017 13:37:34
Prinses Amalia Windpark
23-02-2017 12:37:47
23-02-2017 19:18:45
0.00 MW
Unplanned
Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
20-11-2016 12:38:35
Prinses Amalia Windpark
20-11-2016 11:38:40
20-11-2016 16:00:00
0.00 MW
Unplanned
 


Windfarm has been stopped due to high windspeed( >25 m/s) and will start up when the windspeed drops 
1 to 50 of 57 records
previous12next
Disclaimer: This information is given based on the best estimate of Eneco and has no pretense of being reliable or representative for any market developments. Any use of this information, as a whole or any part thereof, by any person or company without the EXPLICIT consent of Eneco is for that persons or companies own risk and responsibility. Eneco makes no representation or warranty of any kind concerning accuracy or other potential errors in the information. Eneco disclaims all warranties with regard to this information. In no event shall Eneco be liable for any specific, indirect or consequential damages whatsoever resulting from loss profits caused by, or in connection with, the use of this information.